Question: Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
- 1. Concrete
- 2. Loose sand
- 3. Asphalt
- 4. Firm earth
Question: Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
- 1. Ice
- 2. Concrete
- 3. Loose sand
- 4. Earth
Question: An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________________?
- 1. Rs. 8,43,750/-
- 2. Rs. 8,75,000/-
- 3. Rs. 10,50,000/-
- 4. Rs. 11,56,250/-
Question: Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
- 1. Both A and R are true and R is the correct explanation of A
- 2. Both A and R are true but R is not the correct explanation of A
- 3. A is true but R is false
- 4. A is false but R is true
Question: For a given size of bucket, the ideal output of a dragline will be least in_______________?
- 1. Moist loam
- 2. Sand and gravel
- 3. Good common earth
- 4. Wet sticky clay
Question: Which of the following earth moving machines has the shortest cycle time?
- 1. Drag line
- 2. Hoe
- 3. Clam shell
- 4. Dipper shovel
Question: Crash project duration is obtained by summing the________________?
- 1. normal durations for all the activities
- 2. crash durations for all activities
- 3. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
- 4. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Question: The constraints in case of resource smoothening operation would be_______________?
- 1. resources
- 2. project duration time
- 3. both resources and project duration time
- 4. none of the above
Question: Slack time refers to_______________?
- 1. an activity
- 2. an event
- 3. both event and activity
- 4. none of the above
Question: Economic saving of time results by crashing_________________?
- 1. cheapest critical activity
- 2. cheapest non-critical activity
- 3. costliest critical activity
- 4. costliest non-critical activity