Question: In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
- 1. normal distribution curve
- 2. Poisson’s distribution curve
- 3. Beta – distribution curve
- 4. none of the above
Question: Select the correct statement?
- 1. Activity arrows in a CPM network are drawn to scale
- 2. The tail of an arrow represents the finish of an activity
- 3. Arrow bead represents the start of an activity
- 4. none of the above
Question: PERT technique of network analysis is mainly useful for__________________?
- 1. small projects
- 2. large and complex projects
- 3. research and development projects
- 4. deterministic activities
Question: Select the incorrect statement?
- 1. Earliest start of an activity is the early event time of the node it leaves.
- 2. Latest finish of an activity is the late event time of the node it enters.
- 3. Latest start of an activity is its latest finish minus its duration.
- 4. none of the above
Question: Select the incorrect statement?
- 1. Start float and finish float are always equal
- 2. Total float can be either start float or finish float
- 3. Start float and finish float need not be equal
- 4. Start float and finish float are the differences between activity times and not event times
Question: Select the incorrect statement?
- 1. A critical path always begins at the very first event
- 2. A critical path always terminates at the last event
- 3. Critical activities control the project duration
- 4. Critical activity is the one for which free float is zero
Question: The minimum width of the fire escape stairs shall be?
- 1. 1.00 m
- 2. 1.25 m
- 3. 1.5 m
- 4. 2.0 m
Question: The original record of a business transaction is recorded in this book_____________?
- 1. Work book
- 2. Journal
- 3. Ledger
- 4. Account book
Question: All the proceeds which are received by the business as a result of the sale of goods is called _________________?
- 1. Net income
- 2. Gross income
- 3. Net revenue
- 4. Total sales
Question: All are classified under direct labor expenses EXCEPT one. Which one ?
- 1. Inspection cost
- 2. Testing cost
- 3. Assembly cost
- 4. Supervision cost