Question: The constraints in case of resource smoothening operation would be_______________?
- 1. resources
- 2. project duration time
- 3. both resources and project duration time
- 4. none of the above
Question: Slack time refers to_______________?
- 1. an activity
- 2. an event
- 3. both event and activity
- 4. none of the above
Question: Economic saving of time results by crashing_________________?
- 1. cheapest critical activity
- 2. cheapest non-critical activity
- 3. costliest critical activity
- 4. costliest non-critical activity
Question: The direct cost of a project with respect to normal time is________________?
- 1. minimum
- 2. maximum
- 3. zero
- 4. infinite
Question: The time with which direct cost does not reduce with the increase in time is known as_________________?
- 1. crash time
- 2. normal time
- 3. optimistic time
- 4. standard time
Question: What estimate would you give for the variance in above problem ?
- 1. 81
- 2. 54
- 3. 36
- 4. 9
Question: The independent float affects only_______________?
- 1. preceding activities
- 2. succeeding activities
- 3. the particular activity involved
- 4. none of the above
Question: Free float for any activity is defined as the difference between__________________?
- 1. its earliest finish time and earliest start time for its successor activity
- 2. its latest start time and earliest start time
- 3. its latest finish time and earliest start time for its successor activity
- 4. its earliest finish time and latest start time for its successor activity
Question: Total float for any activity is defined as the difference between________________?
- 1. its latest finish time and earliest start time for its successor activity
- 2. its latest start time and earliest start time
- 3. its latest start time and earliest finish time
- 4. its earliest finish time and earliest start time for its successor activity
Question: Free float is mainly used to_________________?
- 1. identify the activities which can be delayed without affecting the total float of preceding activity
- 2. identify the activities, which can be delayed without affecting the total float of succeeding activity
- 3. establish priorities
- 4. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities