Question: The constraints in case of resource smoothening operation would be_______________?
  • 1. resources
  • 2. project duration time
  • 3. both resources and project duration time
  • 4. none of the above
Question: Slack time refers to_______________?
  • 1. an activity
  • 2. an event
  • 3. both event and activity
  • 4. none of the above
Question: Economic saving of time results by crashing_________________?
  • 1. cheapest critical activity
  • 2. cheapest non-critical activity
  • 3. costliest critical activity
  • 4. costliest non-critical activity
Question: The direct cost of a project with respect to normal time is________________?
  • 1. minimum
  • 2. maximum
  • 3. zero
  • 4. infinite
Question: The time with which direct cost does not reduce with the increase in time is known as_________________?
  • 1. crash time
  • 2. normal time
  • 3. optimistic time
  • 4. standard time
Question: What estimate would you give for the variance in above problem ?
  • 1. 81
  • 2. 54
  • 3. 36
  • 4. 9
Question: The independent float affects only_______________?
  • 1. preceding activities
  • 2. succeeding activities
  • 3. the particular activity involved
  • 4. none of the above
Question: Free float for any activity is defined as the difference between__________________?
  • 1. its earliest finish time and earliest start time for its successor activity
  • 2. its latest start time and earliest start time
  • 3. its latest finish time and earliest start time for its successor activity
  • 4. its earliest finish time and latest start time for its successor activity
Question: Total float for any activity is defined as the difference between________________?
  • 1. its latest finish time and earliest start time for its successor activity
  • 2. its latest start time and earliest start time
  • 3. its latest start time and earliest finish time
  • 4. its earliest finish time and earliest start time for its successor activity
Question: Free float is mainly used to_________________?
  • 1. identify the activities which can be delayed without affecting the total float of preceding activity
  • 2. identify the activities, which can be delayed without affecting the total float of succeeding activity
  • 3. establish priorities
  • 4. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities