pKmcqsquiz

Civil Engineering Mcqs

Pagination on API result
Question: If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
  • 1. 3.5 and 5/6
  • 2. 5 and 25/36
  • 3. 3.5 and 25/36
  • 4. 4 and 5/6
Question: In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
  • 1. 2
  • 2. 4
  • 3. 8
  • 4. 7
Question: Earliest finish of an activity is always_______________?
  • 1. greater than earliest event time of the following node
  • 2. less than earliest event time of the following node
  • 3. less than or equal to earliest event time of the following node
  • 4. greater than or equal to earliest event time of the following node
Question: In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
  • 1. normal distribution curve
  • 2. Poisson’s distribution curve
  • 3. Beta – distribution curve
  • 4. none of the above
Question: Select the correct statement?
  • 1. Activity arrows in a CPM network are drawn to scale
  • 2. The tail of an arrow represents the finish of an activity
  • 3. Arrow bead represents the start of an activity
  • 4. none of the above
Question: PERT technique of network analysis is mainly useful for__________________?
  • 1. small projects
  • 2. large and complex projects
  • 3. research and development projects
  • 4. deterministic activities
Question: Select the incorrect statement?
  • 1. Earliest start of an activity is the early event time of the node it leaves.
  • 2. Latest finish of an activity is the late event time of the node it enters.
  • 3. Latest start of an activity is its latest finish minus its duration.
  • 4. none of the above
Question: Select the incorrect statement?
  • 1. Start float and finish float are always equal
  • 2. Total float can be either start float or finish float
  • 3. Start float and finish float need not be equal
  • 4. Start float and finish float are the differences between activity times and not event times
Question: Select the incorrect statement?
  • 1. A critical path always begins at the very first event
  • 2. A critical path always terminates at the last event
  • 3. Critical activities control the project duration
  • 4. Critical activity is the one for which free float is zero
Question: The minimum width of the fire escape stairs shall be?
  • 1. 1.00 m
  • 2. 1.25 m
  • 3. 1.5 m
  • 4. 2.0 m

Search

Category

Subjects