Civil Engineering Mcqs
Question: If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
- 1. 3.5 and 5/6
- 2. 5 and 25/36
- 3. 3.5 and 25/36
- 4. 4 and 5/6
Question: In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
- 1. 2
- 2. 4
- 3. 8
- 4. 7
Question: Earliest finish of an activity is always_______________?
- 1. greater than earliest event time of the following node
- 2. less than earliest event time of the following node
- 3. less than or equal to earliest event time of the following node
- 4. greater than or equal to earliest event time of the following node
Question: In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
- 1. normal distribution curve
- 2. Poisson’s distribution curve
- 3. Beta – distribution curve
- 4. none of the above
Question: Select the correct statement?
- 1. Activity arrows in a CPM network are drawn to scale
- 2. The tail of an arrow represents the finish of an activity
- 3. Arrow bead represents the start of an activity
- 4. none of the above
Question: PERT technique of network analysis is mainly useful for__________________?
- 1. small projects
- 2. large and complex projects
- 3. research and development projects
- 4. deterministic activities
Question: Select the incorrect statement?
- 1. Earliest start of an activity is the early event time of the node it leaves.
- 2. Latest finish of an activity is the late event time of the node it enters.
- 3. Latest start of an activity is its latest finish minus its duration.
- 4. none of the above
Question: Select the incorrect statement?
- 1. Start float and finish float are always equal
- 2. Total float can be either start float or finish float
- 3. Start float and finish float need not be equal
- 4. Start float and finish float are the differences between activity times and not event times
Question: Select the incorrect statement?
- 1. A critical path always begins at the very first event
- 2. A critical path always terminates at the last event
- 3. Critical activities control the project duration
- 4. Critical activity is the one for which free float is zero
Question: The minimum width of the fire escape stairs shall be?
- 1. 1.00 m
- 2. 1.25 m
- 3. 1.5 m
- 4. 2.0 m